Connect a purging-equipped PacWizz to the tank, pressure sensor, and remote motorized ball-valve, with a suitable exhaust route outside.
What you need
Tank purging uses the Remote Motorized Ball-valve (RMB) supplied with purging versions of the PacWizz. It controls the vent path during the pressurize-and-vent sequence.
You also need a suitable regulated gas supply, the Brite hose, the Foot Pressure Sensor, tank fittings, an appropriate tank PRV, and a safe outside exhaust route.
Do not start a purge without appropriate ventilation/extraction and safe outside venting. CO₂ and N₂ releases can displace breathable air. Do not leave a tank purging overnight. Read Safety & Site Requirements first.
Tank-mounted valve arrangement
The manual illustrates the following arrangement:
- Connect the regulated gas supply to the PacWizz CO₂ IN connection.
- Connect the Brite hose to the tank's foot connection for gas injection, as shown below.
- Fit the Foot Pressure Sensor at the CIP arm tee and connect its cable to the PacWizz so tank pressure can be monitored.
- Fit the RMB to the CIP arm's vent path and connect its control cable to the unit.
- Route the RMB exhaust outside through suitable hose/pipework.
- Confirm the required gas, sensing, and exhaust paths are open and correctly connected before selecting Tank Purge.

Gas enters at the tank foot; pressure is measured and gas is vented at the CIP arm. This arrangement differs from the packaging connections.
Recommended outside-venting arrangement
For convenient outside venting, the manual recommends permanently mounting the RMB in a suitable location and running:
Tank CIP arm → hose to RMB inlet → RMB outlet → hose/pipework to outside
The gas supply and pressure-sensor arrangement remain as described above. Confirm the complete vent route is suitable for the gas volume and flow before running a purge.

The key requirement is a continuous, suitable exhaust route outside, rather than discharging purge gas into the workspace.
Connection checklist
- Your unit is equipped for purging and has the RMB connected.
- The tank is correctly assembled and has its appropriate PRV fitted.
- Gas supply enters CO₂ IN and the Brite hose goes to the correct tank connection.
- The Foot Pressure Sensor measures tank pressure and its cable is connected.
- The RMB control cable is connected and its exhaust route is correctly installed.
- Required isolation valves are correctly positioned and the vent route is unobstructed.
- Ventilation/extraction, alarms as appropriate, and hearing protection are ready.
- Someone will supervise the run; the purge will not be left running overnight.
If your fittings or supplied hardware differ from these illustrations, ask BrewWizz to confirm the arrangement before operating.
Continue to Running a Tank Purge.